Site preparation for containerised battery storage
Civil works, cable routes and thermal clearance decide more commissioning days than the battery itself. A short checklist for the weeks before delivery.

Most containerised storage delays we see are civil rather than electrical. The pad is poured late, the cable trench crosses a drainage line, or the container is landed without clearance for the cooling unit doors.
Confirm the pad dimensions, anchor pattern and drainage slope against the final general arrangement drawing before the container is booked for transport.